Corscale commends campus cooling

Corscale Data Centers approves IST of Airedale by Modine cooling solutions on 72MW Gainesville Crossing Data Center.

Corscale is moving closer to the opening of its initial 72MW data center at Gainesville Crossing Data Campus in Virginia, US, following the successful integrated systems testing (IST) of the recently installed Airedale by Modine cooling solution.

Advising on all areas of design, installation and operations, Airedale by Modine has worked closely with Corscale and their approved contractors.to maximize system efficiencies. Following the approval of all four phases of IST testing, the specialist US commissioning agent appointed by Corscale has commended Airedale, noting that they have gone above and beyond their remit to drive optimization and efficiency gains.

The independent commissioning agent was appointed to manage the testing and handover of this project, and they split the testing schedule into four 18MW data halls for increased scrutiny. With full expectation of the equipment to perform in all conditions, they put the fan wall units and chillers to the test in emergency simulations, for example fast-start and sequencer testing.

For a fast-start test, the power is switched off and reinstated after 30 seconds by a generator. An uninterruptible power supply (UPS) restores the 18MW power feed in the data hall, whilst the chiller system has to return to full load and remove the build-up of heat that occurred in the 30 seconds downtime. Sequencer testing involves deliberately ‘failing’ a chiller to ensure the next chiller in the sequence handles the heat load. Other critical scenarios are also tested and reported back to both Corscale and the unnamed hyperscale client who will eventually lease the data center space. The feedback from these reports has been exceptional, recognizing Airedale’s expertise and willingness to drive efficiencies further.

Airedale was appointed by Corscale because of its innovative chiller economizer technology, paired with its in-depth knowledge and understanding of the data center industry. The order for the first data center at Gainesville Crossing Data Campus includes 56 OptiChillTM chillers, 256 AireWallTM fan wall units, and 8 SmartCoolTM computer room air handling units, providing 72 MW of cooling.

Phase one of testing started at the back end of 2023, and with all four phases now completed and signed off, the data center will soon be handed over to Corscale.

Nic Bustamante, Chief Technology Officer for Corscale said,

“We have been consistently reassured by Airedale’s technical expertise and commitment, seeing them go above and beyond, sharing their knowledge and experience with other specialist contractors to develop the most efficient and effective system for our clients.”

Rob Bedard, General Manager of Airedale by Modine North America said,

“Working with Corscale is a privilege that allows us to form a collaborative working environment with their appointed agencies and end-user clients. Such transparency and ease of communication has afforded us all the opportunity to further enhance efficiencies and maximize opportunities for sustainability gains. We look forward to undertaking more great work with Corscale on this and future projects.”

32 mtu gensets at Eco Data Center in Falun ensure uninterrupted power supply. Using HVO (Neste MY...
Talent and training partner, mthree, which supports major global tech, banking, and business...
With cutting-edge high thermal efficiency for sustained GPU performance, the Precision...
Lennox, a leader in energy-efficient climate control solutions, is launching a new business to...
Company scales existing manufacturing and integration footprint from 7000m2 to 12,000m2 in response...
Funding will help enable Accelsius to keep up with increasing demand for its proprietary NeuCool...
According to a new report from Bloomberg Intelligence (BI), EDF, Rolls Royce and other companies...
New research has revealed that CEOs across key European countries are shifting timescales and...