Organisations should plan for the infinite data centre

The increasing business demands on IT mean that data centre managers must plan to increase their organisation’s computing and storage capacity at a considerable rate in the coming years, according to Gartner, Inc. Organisations that plan well can adjust to rapid growth in computing capacity without requiring more data centre floor space, cooling or power and realise a substantial competitive advantage over their rivals.

“The first mistake many data centre managers make is to base their estimates on what they already have, extrapolating out future space needs according to historical growth patterns,” said David Cappuccio, research vice president at Gartner. “This seemingly logical approach is based on two flawed assumptions: that the existing floor space is already being used properly and usable space is purely horizontal.”


To ensure maximum efficiency, data centre growth and capacity should be viewed in terms of computing capacity per square foot, or per kilowatt, rather than a simple measure of floor space. A fairly typical small data centre of 40 server racks at 60 per cent capacity, housing 520 physical servers and growing in computing capacity at 15 per cent each year, would require four times as much floor space in 10 years.


“With conventional thinking and the fear of hot spots at the fore, these 40 racks, or 1,200 square feet of floor space, become nearly 5,000 square feet in just 10 years, with associated costs,” said Mr Cappuccio. “A data centre manager who rethinks his organisation’s floor plans, cooling and server refreshes can house the increased computing capacity in the original floor space and help meet growing business needs indefinitely. We will witness small data centre environments with significant computing growth rates maintaining exactly the same footprint for the next 15 to 20 years.”


In this scenario, Gartner recommends upgrading the existing server base to thinner 1U (one unit) height servers or even sleeveless servers, while increasing rack capacity to 90 per cent on average by using innovative floor-size designs and modern cooling methods, such as rear door heat exchanger cooling (RDHx), to mitigate concerns over hot spots.. Implementing an RHDx system can also reduce the overall power consumption of a data centre by more than 40 per cent, since high volumes of forced air are no longer required to cool the equipment.


“An initial investment in planning time and technology refresh can pay huge dividends in the mid-to-long term for businesses anticipating a continuous growth in computing capacity needs,” said Mr Cappuccio.


The evolution of cloud computing adoption will also provide relief for growing data centre requirements and as the technology becomes more established, an increasing proportion of data centre functions will migrate to specialist or hybrid cloud providers. This further increases the likelihood of an organisation making use of the same data centre space in the future, generating significant cost savings and competitive business advantages.
 

First of its kind research, in partnership with Canalys, offers deep insights into some of the...
According to a recently published report from Dell’Oro Group, worldwide data center capex is...
Managed service providers (MSPs) are increasing their spending by as much as 70% to meet growing...
Coromatic, part of the E.ON group and the leading provider of robust critical infrastructure...
Datto’s Global State of the MSP: Trends and Forecasts for 2024 underscores the importance of...
Park Place Technologies has appointed Ian Anderson as Senior Director, Channel Sales, EMEA.
Node4 has passed the ISO 27017 and ISO 27018 audits, reinforcing its dedication to data security,...
Park Place Technologies has acquired Xuper Limited, an IT solutions provider based in Derby, UK.